Case Summary:
Bankey
Lal Prasad vs. BSES
Utilities: Complainant
faced difficulties in getting water and electricity connection to his house.
During the course of the proceedings and hearings, BSES informed that electric
meter was installed on 12.08.16 at the residence of the Complainant.
Complainant did not approach the Court after this, and as Delhi Jal Board
hasn’t denied the complainant the water connection aft he formalities have been
completed, complaint was closed.
Order / Judgement:
In the Court of State Commissioner for
Persons with Disabilities
National
Capital Territory of Delhi
25-
D, Mata Sundari Road, Near Guru Nanak Eye Centre, New Delhi-2
[Vested with powers of Civil Court under the
Rights of Persons with Disabilities Act,
2016]
Case
No. 4/1217/2016/Wel./CD/ 1481-83 Dated:
02.08.2017
In
the matter of:
Sh.
Bankey Lal Prasad
Plot.
No. 38, Pratap Enclave,
Gurdwara
Road, Mangal Bazar Gali,
Mohan
Garden, New Delhi-110059 ................
Complainant
Versus
The
Chairman (BSES)
BSES
Rajdhani Power Ltd,
BSES
Bhawan, Nehru Place,
New
Delhi-110019
The Chief Executive Oficer,
Delhi Jal Board,
Varunalaya, Jhandewalan,
Karol Bagh, Delhi-110005 ………...…Respondents
ORDER
The above named complainant, a person with 59% loco motor
disability, vide his complaint dated 03.03.2016 submitted that he is a R/o Plot
No. 38, Pratap Enclave, Gurdwara Road, Mangal Bazar Gali, Mohan Garden, New
Delhi-110059. He has not been provided
an electric connection so far. The
reason for the same appears to be that the plot was purchased in the name of
his father for which the GPA was done in the name of the wife of his younger
brother. The DGM who he approached, told
him to get a letter from the Court of Commissioner for Persons with
Disabilities because as per the order of Hon’ble High Court dated 27.01.2016,
electric connection can be given to a person who has Ration Card, Identity
Proof, Telephone or any other such proof at the address. The complainant requested that he be provided
with the electric and water connection in his house.
2. The complaint was taken up with the respondents vide
communication dated 17.03.2016 followed by reminder dated 08.04.2016. DGM (D) VKP vide his letter dated 29.03.2016
informed that the complainant has been asked to complete commercial formalities
for the new connection. After completion
of the same, BSES will release the new connection as early as possible.
3. As the complainant did not get the electric and water
connections, hearings were also held in the matter. Thereafter, BSES informed that an electric meter
has been installed on 12.08.2016 against CA No.151918348 at the residence of
the complainant vide letter dated 23.08.2016.
As regards the water connection, the complainant informed during the
hearing that he was also in the process of completing the necessary formalities
for water connection. He has not
approached this Court thereafter. As the
water connection can be installed only after completion of the necessary formalities
by the complainant and Delhi Jal Board has not denied him the same. The complaint is closed.
Given under my hand and the seal
of the Court this 2nd day of August,
2017.
(T.D. Dhariyal )
State Commissioner for
Persons with Disabilities