Wednesday, August 9, 2017

Pradeep Raj Vs. The CEO, Delhi Urban Shelter Improvement Board | Case No. 4/1084/2015-Wel/CD/1456-57 | Dated: 08.08.2017

Case Summary:

Pradeep Raj vs. Delhi Urban Shelter Improvement Board

Utilities: Complainant submitted that the Association for Disabled people was running the Night Shelter allotted by the DUSIB. This night shelter was getting electricity from the same connection installed at the community center for marriages and other functions, with no separate meter. Before handing over the night shelter to the DUSIB, the Association approached the Executive Engineer for NoC, and the EE indicated an outstanding bill of 1,12,500/- and also fined the Association for shortage of articles despite these articles being returned. After communications, the respondent reworked the amount payable by the association as Rs. 81,600/- and the Complainant informed that he was satisfied with this. There were no further communications from the Complainant, and the case was closed as the major matter had been resolved.

Order / Judgement: 




In the Court of State Commissioner for Persons with Disabilities
National Capital Territory of Delhi
25- D, Mata Sundari Road, Near Guru Nanak Eye Centre, New Delhi-2
Phone-011-23216002-04, Telefax: 011-23216005, Email: comdis.delhi@nic.in
[Vested with powers of Civil Court under the
Rights of Persons with Disabilities Act, 2016]

Case No. 4/1084/2015-Wel/CD/1456-57                 Dated: 08.08.2017

In the matter of:

Sh. Pradeep Raj
House No. 165, Gali No. 13, 
Balbir Nagar Extension,
Shahdara,  Delhi-110032.                                           .……… Complainant     

                                                                      Versus
The CEO,
Delhi Urban Shelter Improvement Board,
A-Block, IInd Floor , Vikas Bhawan-II
Upper Bela Road, Delhi-110054.                                   …...…Respondent
 
            
ORDER

               The above named complainant, a person with locomotor disability vide his complaint dated 12.08.2015 submitted that the Association for Disabled People which works for persons with disabilities, was running the Night Shelter allotted by the Delhi Urban Shelter Improvement Board (DUSIB)  at Padam Nagar from December, 2011 to January, 2015.  The Night Shelter was getting the electricity from the same connection which was installed at the Community Centre used for marriages and other functions.  The NDPL did not allot a separate electric meter to the Night Shelter as the bills of lacs of rupees were outstanding against the Community Centre.  As per the complainant, before handing over the Night Shelter to DUSIB on 05.01.2015, the Association approached the Executive Engineer (EE) for NOC.  The EE indicated an outstanding bill of Rs. 1,12,500/-against the Association.  Besides, they had imposed  fine for shortage of some articles like daries, blankets etc. although these had been returned to the Officers of DUSIB.  The complainant submitted that appropriate action may be taken against the DUSIB Officials and the outstanding bills and the fine be withdrawn. 

2.           The complaint was taken up with the respondent vide Notice dated 21.08.2015.  The respondent vide letter dated 03.09.2015 inter-alia submitted that the possession of the said night shelter had been handed over to the Association on 19.11.2011 and the contract of allotment expired on 30.11.2014.  As per the information provided by the concerned Civil Division C-10, the booking of the community hall for functions was for a period of 191 days out of total 1110 days from 21.12.2011 to 05.01.2015.  The total consumption of the electricity was worth Rs. 1.50 lacs as per actual load installed and Rs. 1,12,500/- was worked out based on the consumption by the Agency, which is 75% of the total amount.  As the agency did not return the materials to the Department, an amount of Rs. 1364/- was ordered to be recovered as the cost of material.  In view of the submissions, the respondent requested to reject the complaint. 

3.           The complainant vide his rejoinder dated 24.09.2015, objected to charging of  75% of the bills from the Association in view of the fact that a large number of marriages and other parties used to be held in the Community Centre. The association had applied for an electricity connection twice; but the same was not provided.

4.           Thereafter, the parties were heard by the then Commissioner for Persons with Disabilities on 02.11.2015 and 26.11.2015.  The respondent reworked the amount payable by the association as  Rs. 81,600/-.  The complainant informed vide his letter dated 28.12.2015 that the Association was satisfied with the modification of electricity bill and did not want further action in the matter.  However, the complainant in a subsequent communication requested that Rs. 5000/- which DUSIB had taken for re-charging the meter should also be returned which was taken with the respondent, who vide letter dated 09.01.2017 informed that two letters dated 28.12.2016 and 06.01.2017 had been written to the complainant for producing the relevant documents to claim his case. But he has not turned up with the documents to resolve the issue.  There has not been any correspondence from the complainant after 10.10.2016 and when the complainant was contacted on phone, he informed the Office of State Commissioner for Persons with Disabilities that he did not want to pursue the matter as the major issue has already been resolved.
              
                     In the light of the above, the matter is closed.

              Given under my hand and the seal of the Court this 4th  day of August,2017.     


           (T.D. Dhariyal )
                          State Commissioner for Persons with Disabilities















No comments:

Post a Comment